Hanoi's first metro line: Hurdles need clearing quickly

Hanoi's first metro line still depends on the safety evaluation from the French consultancy Apave-Certifier-Tricc (ACT) consortium before it can be handed over to the Ministry of Transport.

Relevant authorities are trying to clear all hurdles to put the Cat Linh – Ha Dong urban railway into motion as soon as possible so that pressure on the city's transport infrastructure could be eased, Kinhtedothi.vn reported.

The test run of the Cat Linh - Ha Dong urban rail line was due to have started on June 30, 2015. Thus, it has been delayed by half a decade.

In late March 2020, the Hanoi Party Committee and the Ministry of Transport agreed to set up a task force to build a plan for the project’s final works. Besides, the two parties agreed on a plan to carry out "conditional acceptance" for the Cat Linh - Ha Dong railway project and thoroughly address all pending issues related to China Railway Sixth Group - the general contractor of the project.

 The Cat Linh - Ha Dong urban railway needed to be put into commercial run. Photo: Nguyen Quy

Cao Sy Kiem, a former governor of the State Bank of Vietnam, told Kinhtedothi.vn that the Chinese general contractor’s irresponsibility is to be blamed for the project delay.

“The general contractor has not shown the goodwill needed to solve issues of the project even though they know we really want to put the project into commercial operation as soon as possible," Kiem said.

Sharing the same view, Nguyen Xuan Thuy, a transport expert, said that the general contractor also showed signs of deliberately extending the time to shirk responsibility for the delay of the project.

The project still depends on the safety evaluation from the French consultancy Apave-Certifier-Tricc (ACT) consortium before it can be handed over to the Ministry of Transport.

“The addition of dossiers for evaluation is very simple and does not take too much time because we have modern machines and techniques for measurement and evaluation. We only need about half a month to a month, instead of half a year or several years as they have warned,” Thuy argued.

“The Ministry of Transport must also take responsibility for the failure to put the project into operation on time. The ministry must clarify the reasons for the delay," Thuy stressed.

The Cat Linh - Ha Dong project is a first urban railway project in Vietnam. It must be evaluated and certified for system safety by an independent consultancy organization first. Then, the Vietnam Register will evaluate safety dossiers and issue evaluation certificate before the project can start the commercial operation phase.

The railway is one of the key public transport projects in Hanoi. Since September 2018, its rolling stock of 13 trains has been tested, with the average speed of 35 kilometers per hour.

The railway is 13.5 kilometers long from Cat Linh Station in downtown Dong Da district to Yen Nghia Station in the southwestern Ha Dong district, and uses standard-gauge rail track (1,435mm).

Reactions:
Share:
Trending
Most Viewed
Related news
Thủ khoa, á khoa thi đánh giá tư duy đợt 2 tiếp tục đến từ Trường chuyên Bắc Ninh

Thủ khoa, á khoa thi đánh giá tư duy đợt 2 tiếp tục đến từ Trường chuyên Bắc Ninh

Trước đó, Vũ Minh Đức - học sinh lớp 12 toán 2 Trường THPT chuyên Bắc Ninh - trở thành thủ khoa kỳ thi đánh giá tư duy đợt 1 với 98,61/100 điểm - đây là điểm số cao nhất từ trước tới nay, xô đổ mọi kỷ lục của các thủ khoa những năm trước.

Vietnam strengthens semiconductor ties with SEMI SEA

Vietnam strengthens semiconductor ties with SEMI SEA

Vietnam is urging international organizations to connect global investors and experts with local businesses and research partners.

Tôi khổ vì nhà đẻ, hạnh phúc vì nhà chồng

Tôi khổ vì nhà đẻ, hạnh phúc vì nhà chồng

Từ khi lấy chồng, tôi chỉ cần nấu ăn hoặc có khi chồng nấu, còn lại dọn dẹp nhà cửa, đi chợ, rửa chén, giặt đồ… đều do chồng làm.

Lợi ích đặc biệt của giá đỗ không phải ai cũng biết

Lợi ích đặc biệt của giá đỗ không phải ai cũng biết

Giá đỗ rất giàu vitamin, cung cấp protein và chất chống oxy hóa hỗ trợ sức khỏe, tốt cho nam giới.

Khởi đầu từ vấn đề của khách hàng - triết lý phát triển công nghệ của Grab

Khởi đầu từ vấn đề của khách hàng - triết lý phát triển công nghệ của Grab

(Dân trí) - Đối với công nghệ, cách tiếp cận của Grab luôn bắt đầu từ việc thấu hiểu vấn đề và nhu cầu thực sự của khách hàng để tìm ra giải pháp phù hợp.

Tài khoản Siêu lợi suất phù hợp khách hàng nào? - Báo VnExpress

Tài khoản Siêu lợi suất phù hợp khách hàng nào? - Báo VnExpress

Tôi kinh doanh cửa hàng gia dụng, tiền trong tài khoản thường xuyên giao dịch, vậy tôi có sử dụng tài khoản Siêu lợi suất được không? Hồng Nhung (36 tuổi, Kiên Giang).

Khách hàng có thể giao dịch dễ dàng cùng Techcombank tại hệ thống WinMart

Khách hàng có thể giao dịch dễ dàng cùng Techcombank tại hệ thống WinMart

Từ tháng 1-2025, chuỗi siêu thị/cửa hàng WinMart/WinMart+/WiN (thuộc WinCommerce) chính thức trở thành đại lý ngân hàng của Techcombank.

Global Student Fashion Week to make Hanoi a rendezvous of int'l young designers

Global Student Fashion Week to make Hanoi a rendezvous of int'l young designers

With the theme Sustainable Fashion, the event will demonstrate skillful design techniques, convey strong messages about environmental responsibility, recycling culture and application of technology in modern fashion.