Drastic measures needed to realize disbursement target of public funds

As the disbursed amount between January and August was equivalent to 50.7% of the target, the government is under pressure to spend the remaining 50% in the remaining four months.

Despite improvements in disbursement of public funds, the progress remains slower than expected and requires huge efforts to meet the government target by year-end.

 Drastic measurse are required for Vietnam to realize the disbursement target of public funds this year. Photo: Thanh Hai. 

 

In the first eight months of 2020, the disbursed amount of public investment stood at VND250 trillion (US$10.8 billion), up 30.4% year-on-year but equivalent to only 50.7% of the target.

 

The government, therefore, is under pressure to expend the remaining 50% of public investment funds in the remaining four months.

 

As of present, the disbursement progress lies on the implementation of major infrastructure projects, including the Eastern North-South expressway project, Long Thanh International Airport, or the upgrade of runways of international airports of Tan Son Nhat and Noi Bai, among others.

 

Meanwhile, projects financed by the official development assistance (ODA) fund such as the Ben Luc – Long Thanh expressway and urban railways are lagging behind schedule, resulting in a low disbursement rate.

 

Minister of Planning and Investment Nguyen Chi Dung attributed the slow disbursement to changes in policies, difficulties in site clearance, as well as lack of capabilities from project owners and contractors.

 

Regarding ODA projects, Mr. Dung said many are lacking legal grounds to start construction works, mainly due to adjustments to the financing agreements and investment procedures.

 

Mr. Dung added the Covid-19 pandemic has also impacted foreign-invested projects, specifically in importing equipment, machinery, and the entry of foreign experts.

 

Amid mounting difficulties, Prime Minister Nguyen Xuan Phuc has reiterated the government’s determination to fully disburse entirely the target amount of public funds, adding this is key to boost economic growth during the Covid-19 crisis.

 

In a meeting late August, Mr. Phuc warned officials would face disciplinary actions if their ministries and localities fail to realize their respective disbursement targets of public investment funds for this year,

 

On this issue, Minister of Planning and Investment Dung also said the government is willing to transfer state capital from projects whose disbursement is lagging behind those with faster pace.

 

Among measures to boost the disbursement performance, Mr. Dung said both central and local governments would hold monthly meetings to address related issues.

 

In a meeting with the ADB’s Country Director to Vietnam Andrew Jeffries on September 17, PM Phuc requested the bank’s support in disbursing US$900 million to ADB-funded projects in 2020.

Reactions:
Share:
Trending
Most Viewed
Related news
Tỷ phú Elon Musk: Tổng thống Zelensky nên từ chức

Tỷ phú Elon Musk: Tổng thống Zelensky nên từ chức

(Dân trí) - Tỷ phú Elon Musk, cố vấn thân cận của Tổng thống Mỹ Donald Trump, kêu gọi nhà lãnh đạo Ukraine Volodymyr Zelensky từ bỏ quyền lực.

Prime Minister orders the completion of Gia Binh Airport-Hanoi route in 2 years

Prime Minister orders the completion of Gia Binh Airport-Hanoi route in 2 years

Building the airport and its infrastructure will help spur socioeconomic growth in the North.

Party chief experiences Ho Chi Minh City’s first metro line

Party chief experiences Ho Chi Minh City’s first metro line

The Party chief’s visit is significant after the National Assembly approved a resolution on February 19 to pilot mechanisms for Ho Chi Minh City’s urban railway development.

Around 70,000 new apartments to be delivered in Hanoi

Around 70,000 new apartments to be delivered in Hanoi

Hanoi’s apartment market is on the rebound and entering a new cycle, with prices remaining high due to strong demand.

Hanoi greenlights road linking Gia Binh Airport

Hanoi greenlights road linking Gia Binh Airport

The road construction project is in line with the city's general planning guidelines and ensures connectivity with existing transportation networks outlined in approved planning schemes.

Lao Cai, Hanoi, Haiphong Railway Project submitted to National Assembly

Lao Cai, Hanoi, Haiphong Railway Project submitted to National Assembly

The line is expected to boost socio-economic growth along the Lao Cai-Hanoi-Haiphong corridor, improve national and international rail links, and support industrialization and modernization.

Accelerate Hanoi's infrastructure development by maximizing resources

Accelerate Hanoi's infrastructure development by maximizing resources

Hanoi is pushing ahead with a major plan to mobilize and effectively utilize resources for infrastructure development.

Hanoian needs $8,000 monthly on average to buy home: analysis

Hanoian needs $8,000 monthly on average to buy home: analysis

A middle-income family earning around US$1,200 a month will struggle to afford a new home in Hanoi.